The question may seem strange to voters who just gave Lennar the green light to redevelop the Shipyard and Candlestick Point by voting Yes on Proposition G.
But it sure looks like there’s a major financial problem at Lennar’s construction site on Parcel A of the Shipyard ( the first piece of land on the former naval base to be developed), judging from documents obtained from the City.
“Without the requested $25,021,079 Infill grant allocation, our infrastructure project faces a serious risk of being mothballed,” wrote Stephen Maduli-Williams, Deputy Executive Director of Community and Economic Development for the San Francisco Redevelopment Agency, on May 23, 2008. “The project would face increased costs from work stoppage, remobilization efforts and substantial change orders.”
Maduli-Williams was writing to Wanda Yepez, a grant program manager at the California Department of Housing and Community Development, to appeal a grant application that Yepez determined as ineligible a week earlier, on May 16, 2008.
In his May 23 appeal, Maduli Williams stated that, “In addition to setting national benchmarks in the percentage (in terms of total units developed) and affordability level of housing units created, this project sets benchmarks with its level of developer commitment/investment as well as other community benefits (Legacy Fund).”
“Up until this point,” Maduli-Williams continued, “this project has relied upon developer equity and Community Facilities District funds as a funding source for infrastructure costs. If this formula works, other funds would be used to provide much needed affordable housing. If the formula doesn’t work, the project is subject to either a drastic reduction of scale or two to three year postponement, if not longer, without additional sources of capital.”
In her May 16 letter, informing the SFRA that the City is ineligible for a grant, Yepez noted that about 69 percent of the 87 projects that Maduli-Williams requested funds for, had construction dates of May 2008.
Yepez also observed that SFRA’s explanation of why the project needs gap funding indicates that the net result of receiving the grant would be an increase in Legacy funds to $20.9 Million.
“From this information, it is difficult to determine whether this application demonstrates a clear financing gap versus supplanting available funds," Yepez wrote.
As Sup. Chris Daly, who unearthed these documents, told the Guardian, the discovery that the City applied for and was turned down for a $25 million grant to subsidize construction at the Shipyard, raises significant questions whether or not they have the financing to move forward.
“It also casts a very large shadow on the mixed-use development envisioned under the conceptual framework on Proposition G,” Daly told us.
Calls to SFRA’s executive director Fred Blackwell remained unanswered as of the publication of this blog post.
But Maduli-Williams’ May 23 letter offers valuable insights into the potential pitfalls the City faces by having entered into a public-private partnership with Lennar.
As Maduli-Williams writes,, establishing a community facilities district enables the City to make the shipyard available for development.
“While this tool is made powerful by the capture of increased land values, it is also susceptible to changes in the project scope and market,” Maduli-Williams wrote. “Currently, the project has had to absorb a significant increase in soft costs related to unforeseen environmental issues, increased construction and labor costs associated with an extended performance schedule “
According to Maduli-Williams, the net result of these issues is that the purchasing power of the Hunters Point Shipyard CFD has decreased by more than 44 percent, resulting in a gap of roughly $25 million by the 4th quarter of 2008.
Maduli-Williams claims that issuing additional CFDs would be infeasible due to the impact on homeowners’ property taxes, which in turn would result in decreased home values, and further deteriorate the project’s value.
He further notes that the other gap funding alternative, market based debt financing, would be challenging as well, “due to the increased cost of borrowing, as well as the scarcity of available debt for large scale housing projects.”
“This alternative would increase development costs and exacerbate the gap that the Agency seeks to close,” Maduli-Williams wrote. “In addition, additional debt would be considered fiscally imprudent by the Agency and the Developer’s finance committee.”
Maduli-Williams also clarifies how the Legacy Fund is tied directly to the land sales.
“To date, this land value agreement has yet to be confirmed and approved by the Agency. Without this value, the Legacy Fund is merely a projection, which could fluctuate depending on market conditions. As with any development project, the developer’s “return” is not truly known until the land is sold.
Maduli-Williams notes that the Hunters Point Shipyard would not be the first large public-private development project to fail "due to market fluctuations.”
He cites Hudson Yards in New York, City North in Phoenix, Seattle’s Denny’s Triangle as all having faced financial setbacks due to diminishing land values and the market’s reluctance to take on new risks.
“Yet projects such as these hold broader implications for a City’s economic health than the project’s financials," Maduli-Williams wrote. "As a result, a public agency such as SFRA has an obligation to see project through market cycles. Ultimately, the project is left with only one alternative, the Infill and Infrastructure grant from HCD. It is clear that without these funds the project may fail."
Maduli-Williams also intimates that if Phase 1 doesn't go forward, Phase 11--the mixed use project that voters just approved on the june 3 ballot--may also be jeopardized.
“In particular, the failure of Phase 1 may obstruct the delivery of Phase 11 of the Hunters Point Shipyard/Candlestick development project which would bring 10,000 new homes to the community, at least 30 percent of which would be made affordable, as well as hundreds of open space, transit, and jobs to an area that has been deeply neglected for more than 30 years," Maduli-Williams claimed.
Maduli-Williams attached letters from Lennar to SFRA, which as he wrote, “should serve as evidence of the historical infrastructure delays the project has endured over the last 18 months.”
These letters, dated June 14, 2007, July 30, 2007 and November 2007, provide a summary of the issues that caused a delay to the project schedule for grading and retaining walls phase at Parcel A of the Shipyard.
These issues include exceptionally hard bedrock, shutdowns due to naturally occurring asbestos monitoring, greater than average rainfall, electrical design issues, subdrain and storm drain redesigns and Block 56 redesign, for a total of 234 days.
In our previous coverage of Lennar’s failures to properly monitor and control asbestos at Parcel A, the Guardian unearthed a memo in which Lennar admitted that each lost construction day cost at least $40,000.
Lennar also faces millions in unresolved fines from the Bay Area Air Quality Monitoring District for its failures to properly monitor and control asbestos at the Parcel A site.
In her June 10 reply, Yepez notes that the “pocket parks” that Maduli-Williams listed as project amenities in his May 23 grant appeal, do not meet the definition of a public park. Instead, they more closely resemble open space within a development, and as such may not be eligible for tax credits, Yepez warns,
Yepez’ observation raises even more questions about the fiscal viability of Lennar’s Shipyard/Candlestick Point development, in which much of the open space consists of pocket parks. And this latest twist in the development saga has Lennar’s critics accusing them, once again, of being more interested in land banking than redeveloping BVHP.
Stay tuned…
.
digg •
del.icio.us •
sphere •
google
•


Comments (2)
PLEASE HELP US!!!
Support your letter carrier – Postal management is abusive and unfair!
NALC UNION #214 SPONSORS PICKET LINE AGAINST MANAGEMENT ABUSE
PRESS RELEASE
Postal employees and other community organizations will be picketing the Post Office
INFORMATIONAL PICKET LINE
Pacific Carrier Annex
1199 Ortega (corner of 19th Ave)
Friday June 20, 2008
4pm to 7pm
* * * * * * * * * * * * * * * * * *
In October of 2006, employees from USPS facility PCA submitted a petition to Congresswoman Pelosi and Congressman Lantos citing management harassment, hostility and abuse.
In November of 2006, fellow USPS station “180 Napoleon” in San Francisco endured a murder-suicide involving a letter carrier and a supervisor. Many believe it was linked to the increase in abusive conditions in the stations. Many fear it will happen again because there seems to be no way postal employees can rectify the situation.
In March of 2007, USPS management was called into Congresswoman Pelosi’s office to answer charges by 90 employees of widespread harassment, retaliation and abuse at USPS facility PCA under the management of Cecilia Denton. Further petitions from other USPS employees bolstered the charges. Yet in the wake of that meeting neither USPS District Manager Winifred Groux or SF USPS Postmaster Noemi Luna have bothered to address the workforce in words or actions, and abuse has continued unchecked.
Among the harassments:
- An employee takes family leave under FMLA and is told when she tries to return to work that her job has been discontinued and “no work is available.”
- An employee is seriously injured on the job, takes time off to heal, and is told upon returning, “No work available.”
- After weeks of harassment a letter carrier finally breaks down and cries. She is sent home on emergency suspension accused of “disrupting the workroom floor.”
- A carrier is given a letter of warning simply because she advised a co-worker who was being harassed to call Nancy Pelosi.
- An employee is shaken and slapped by a supervisor.
- One employee who participated in the Pelosi petition had to defend herself by filing 20 grievances.
- An elderly carrier was taken to the office for going to get water at the water fountain so she could take her medication. She was chastised and instructed to wait until her break to go get water.
- Carriers are instructed to cancel their doctor appointments and go on their day off.
- Needing investigation are targeted termination of harassed employees.
- Needing investigation is the impact of USPS management retaliation on union shop stewards and employees filing grievances and EEOs.
- Just this past Saturday, June 7th, at USPS Parkside facility located a few blocks from PCA, the police were called in when an employee became frightened of a manager’s aggressiveness and employees were bullied and harangued. A petition was later passed around this station and a grievance filed.
Postal management has delayed grievance processing. Over 200 grievances have been delayed, taking more than one year for steps that should take five weeks. With the grievance process derailed, management is free to commit any number of violations while they target postal employees for any minor infraction.
Yelling, arguing, demeaning remarks, and treating employees with contempt are routine. Many employees are distraught and stressed out and feel they have nowhere to turn for help. Carriers are expected to follow orders without opinion or question. If an individual differs with a supervisor they are often charged with “disrespecting/disobeying a supervisor.”
A substantial increase in firings, suspensions and other discipline are devised to intimidate employees into working faster just so the managers can collect their bonuses.
This summer the National Association of Letter Carriers Branch 214 is trying to raise awareness of the appalling conditions that letter carriers and other postal employees are working under as the postal management is becoming increasingly autocratic and dictatorial. The U. S. Postal Service obviously faces difficult times with a downturn in the economy and decrease in mail volume but postal employees are standing together on Friday June 20, 2008 to say there is absolutely no excuse for the abuse of any employee just to increase productivity.
Please email, if you have questions.
Posted by David Womack | June 12, 2008 12:56 PM
For a comment that is more relevant to this article please see posting "Y'all Got Fooled Again", and others, under "Uh-oh, Lennars 25 million dollar Shipyard Funding Gap", if and when it gets "approved".
Pat Monk.RN. Noe Valley.
patmonkrn@yahoogroups.com
http://groups.yahoo.com/groups/patmonkrn
Posted by Patrick Monk.RN | June 13, 2008 08:43 AM